Construction Projects
Skip to main content Skip to navigation Skip to footer

Construction

Using the Construction and Detours Database

You can search and sort projects by several convenient methods:

  • Filter according to time, choosing from All, Current, Planned or Complete.
  • Keyword Search by street name, project type or any word that may appear in the entry.
  • By column, you can click the heading of any column to sort by that category in either ascending or descending order.​
  • By page, you can move from page to page (ten entries per page) using the buttons at the bottom.

Expand the listing to learn more by clicking the plus + symbol and close it by clicking the minus - symbol.

Street Name Start Date End Date Estimated Duration Description Contact Contractor Status Keywords Filterable Status Sortable Start Date Sortable End Date
Street Name Start Date End Date Estimated Duration Description Contact Contractor Status Keywords Filterable Status Sortable Start Date Sortable End Date
Adanac Avenue (From Campbell Avenue to McKay Avenue) 10/8/2020 12/15/2020 Thursday, October 08, 2020 to Tuesday, December 15, 2020

​Adanac Avenue from Campbell Avenue to McKay Avenue will be closed for sewer, watermain and pavement reconstruction. Local Traffic Only.

Amandeep Bains, P. Eng. Engineer II (519) 255-6100 x6472 D'Amore Construction (2000) Ltd. Current road,sewer,watermain Current All 10/08/2020 00:00:00 12/15/2020 00:00:00
Argyle Road and Richmond Street Intersection (From Argyle Road to Richmond Street) 9/1/2020 9/8/2020 Tuesday, September 01, 2020 to Tuesday, September 08, 2020 The intersection of Richmond Street and Argyle Road is closed to vehicular traffic due to road repairs. Domenic Zucco, Maintenance Supervisor Operations (519) 255-6560 x4230 Pierascenzi Construction Limited Complete road Complete All 09/01/2020 00:00:00 09/08/2020 00:00:00
Banwell Road Corridor Improvements - Phase 1 (From Tecumseh Road East to Palmetto Street) 9/14/2020 12/14/2020 Monday, September 14, 2020 to Monday, December 14, 2020

This project will cover Banwell Road between Tecumseh Road East and Palmetto Street.

Banwell Road Corridor Improvements - Phase 1 includes:

  • Widening to two lanes in each direction, separated by a median
  • Construction of new concrete sidewalks and Multi Use Trail (MUT)
  • Construction of flexible roadway pavement (new asphalt)
  • Installation of street lighting and traffic signals
  • Upgrading the storm sewer/drainage and closing most of the road side-ditches.

The contractor will be providing temporary access to all businesses for the duration of the project.

2205_001 3.pdf2205_001 3.pdf

Wadah Al-Yassiri P. Eng. Project Administrator (519) 255-6100 x6494 SheaRock Construction Group Inc. Current road,sewer,sidewalk Current All 09/14/2020 00:00:00 12/14/2020 00:00:00
Belle Isle View Boulevard (From Edgar Street to St. Rose Avenue) 9/8/2020 12/31/2020 Tuesday, September 08, 2020 to Thursday, December 31, 2020

​Belle Isle View Boulevard, Phase 2, will be closed from Edgar Street to St. Rose Avenue for sewer, pavement, watermain and streetlighting reconstruction.

Janelle Coombs, P. Eng. Engineering II (519) 255-6257 x6407 Amico Infrastructures Inc. Current road,sewer,sidewalk,watermain Current All 09/08/2020 00:00:00 12/31/2020 00:00:00
Bridge Avenue (From Wyandotte Street West to College Avenue) 2/24/2020 5/29/2020 Monday, February 24, 2020 to Friday, May 29, 2020

​The Windsor Utilities Commission will be reconstructing the watermain on Bridge Avenue from Wyandotte Street West to Cul-de-sac south of College Avenue (Ward 2).

2020-061 Bridge Pre-Construction Letter.pdf2020-061 Bridge Pre-Construction Letter.pdf

Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 D'Amore Construction (2000) Ltd. Complete watermain Complete All 02/24/2020 00:00:00 05/29/2020 00:00:00
Broadway Street/Essex Terminal Railway Crossing Pavement Upgrades (From Ojibway Parkway to Essex Terminal Railway) 9/14/2020 10/2/2020 Monday, September 14, 2020 to Friday, October 02, 2020

​Broadway Street will remain closed at the Essex Terminal Railway Crossing west of Ojibway Park for pavement upgrades. Access to businesses is open to traffic by way of Sandwich Street. Ongoing until Friday, October 2, 2020.

Stacey McGuire, P. Eng. Project Administrator (226) 350-4740 DanRuss Contracting Inc. Complete road Complete All 09/14/2020 00:00:00 10/02/2020 00:00:00
Bruce Avenue and Ellis Street (From see above to see above) 8/4/2020 11/13/2020 Tuesday, August 04, 2020 to Friday, November 13, 2020

​Bruce Avenue from Tecumseh Road West to Grove Avenue and Ellis Street from Bruce Avenue to Dougall Avenue are closed for watermain reconstruction. Local traffic only.

Bruce Ellis Pre-Construction Letter.pdfBruce Ellis Pre-Construction Letter.pdf

Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 Major Construction (2000) Ltd. Current road,watermain Current All 08/04/2020 00:00:00 11/13/2020 00:00:00
Byng Road (From Lappan Road to Melinda Street) 9/8/2020 12/31/2020 Tuesday, September 08, 2020 to Thursday, December 31, 2020

​Byng Road from Lappan Avenue to Melinda Street and Lappan Avenue from Byng Road to Turner Road is closed for sewer, pavement and street lighting reconstruction. Local traffic only.

Adam Mourad, P. Eng. (519) 255-6100 x6614 To be determined. Current road,sewer Current All 09/08/2020 00:00:00 12/31/2020 00:00:00
Cabana-Dougall Intersection Detour (From Cabana Road to Dougall Avenue) 8/20/2020 10/30/2020 Thursday, August 20, 2020 to Friday, October 30, 2020

​Construction at the intersection of Dougall Avenue and Cabana Road will see one lane through traffic in all directions. Expects delays. Estimated completion date of October 30, 2020.

Jane He, P. Eng., Engineering (519) 255-6257 x6358 Aecon Current road Current All 08/20/2020 00:00:00 10/30/2020 00:00:00
Cabana Road (From Howard Avenue to Dougall Avenue) 4/13/2020 8/31/2020 Monday, April 13, 2020 to Monday, August 31, 2020

​Cabana Road east and west bound lanes from Howard Avenue to Dougall Avenue will have isolated lane restrictions for the construction of manhole, sewers and road construction.

Jane He, P. Eng. (519) 255-6100 x6358 To be determined. Complete road,sewer,watermain Complete All 04/13/2020 00:00:00 08/31/2020 00:00:00
Cabana Road West (From Dougall Avenue to Mount Carmel Drive) 5/4/2020 9/18/2020 Monday, May 04, 2020 to Friday, September 18, 2020

​Cabana Road West from Dougall Avenue to Mount Carmel Drive will have isolated lane restrictions for Enbridge Gas main and service line construction.

Jane He, P. Eng., Engineering (519) 255-6257 x6358 Enbridge Gas Complete None. Complete All 05/04/2020 00:00:00 09/18/2020 00:00:00
Cabana Road West Phase 3 (From Dougall Avenue to Mount Carmel Drive) 9/21/2020 10/30/2020 Monday, September 21, 2020 to Friday, October 30, 2020

​Cabana Road West from Dougall Avenue to Mount Carmel Drive will have isolated lane restrictions for ENWIN hydro and service pole relocation.

Jane He, P. Eng., Engineering (519) 255-6257 x3658 ENWIN Current road Current All 09/21/2020 00:00:00 10/30/2020 00:00:00
Cadillac Street (From Tecumseh Road East to Alice Street) 8/10/2020 12/15/2020 Monday, August 10, 2020 to Tuesday, December 15, 2020

​Cadillac Street from Tecumseh Road East to Alice Street is closed for sewer, pavement and street lighting reconstruction. Local traffic only

Travis Frickey Technologist Operations (519) 255-6560 x6305 Sterling Ridge Infrastructure Inc. Current road,sewer Current All 08/10/2020 00:00:00 12/15/2020 00:00:00
California Avenue and Pulford Street (From see description to see description) 6/8/2020 8/31/2020 Monday, June 08, 2020 to Monday, August 31, 2020

​California Avenue between Pulford Street and Norfolk Street and Pulford Street between California Avenue and Northway Avenue will be closed for approximately 2 1/2 months for sewer and road reconstruction. Local traffic will be permitted only.

Ian Wilson, P. Eng., MASc Engineer II (519) 255-6100 x6369 Amico Infrastructures Inc. Complete road,sewer Complete All 06/08/2020 00:00:00 08/31/2020 00:00:00
Campbell Avenue (From University Avenue to Martindale Avenue) 8/11/2020 8/11/2020 Tuesday, August 11, 2020

​Campbell Avenue will have lane restrictions between University Avenue and Martindale Avenue for catch basin repairs. Flag persons will be present.

Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 DanRuss Complete catch basin Complete All 08/11/2020 00:00:00 08/11/2020 00:00:00
Campbell Avenue (From Adanac Avenue to Campbell Avenue) 10/21/2020 10/22/2020 Wednesday, October 21, 2020 to Thursday, October 22, 2020

​Campbell Avenue will be reduced to one lane at the intersection of Adanac Avenue for sewer and watermain rehabilitation. A flag person will be present. On Wednesday, October 21 and Thursday, October 22, 2020.

Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 D'Amore Construction (2000) Ltd. Complete sewer,watermain Complete All 10/21/2020 00:00:00 10/22/2020 00:00:00
Central Avenue Off Ramp (From E.C. Row Expressway to Central Avenue) 10/4/2020 10/5/2020 Sunday, October 04, 2020 to Monday, October 05, 2020

​The Eastbound E.C. Row Expressway off-ramp to Central Avenue will be closed for milling and paving work.

Motorists are asked to exit at Walker Road and follow the posted detour sign to get to Central Avenue. Alternatively, motorists can exit at Jefferson Avenue and use either the North or South Service Road to get to Central Avenue.

Michael Cappucci, P. Eng. Contracts Coordinator (519) 255-6326 Mill Am Corporation Complete road Complete All 10/04/2020 00:00:00 10/05/2020 00:00:00
Chilver Road (From Tecumseh Road East to Ypres Avenue) 6/9/2020 8/28/2020 Tuesday, June 09, 2020 to Friday, August 28, 2020

​The Windsor Utilities Commission will be reconstructing the watermain on Chilver Road from Tecumseh Road East to Ypres Avenue. The project should take approximately 10 weeks to complete.

2020-016 Chilver Pre-Construction Letter.pdf2020-016 Chilver Pre-Construction Letter.pdf

Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 Coco Paving Complete watermain Complete All 06/09/2020 00:00:00 08/28/2020 00:00:00
Church Street (From Giles Boulevard West to Caroline Street) 3/23/2020 8/21/2020 Monday, March 23, 2020 to Friday, August 21, 2020

​Church Street will be closed for watermain and road reconstruction. Local traffic only.

Michael Cappucci, P. Eng. Contracts Coordinator (519) 255-6560 x4234 Sherway Construction Complete road,watermain Complete All 03/23/2020 00:00:00 08/21/2020 00:00:00
College Avenue (From Wellington Avenue to Crawford Avenue) 7/6/2020 8/21/2020 Monday, July 06, 2020 to Friday, August 21, 2020

College Avenue will be closed for Road reconstruction between Crawford Avenue and Wellington Avenue.

 

Michael Cappucci, 519-255-6560 Ext 4234 TBD Complete road Complete All 07/06/2020 00:00:00 08/21/2020 00:00:00
College Avenue (From South Street to Brock Street) 10/28/2019 11/30/2019 Monday, October 28, 2019 to Saturday, November 30, 2019

​College Avenue between South Street and Brock Street will be closed for road rehabilitation.

Dimitri Buzinde, Contracts Supervisor Operations (519) 255-6560 x4331 Shearock Construction Complete road Complete All 10/28/2019 00:00:00 11/30/2019 00:00:00
Dominion Boulevard (From E.C. Row Expressway to Northwood Street) 5/6/2020 7/13/2020 Wednesday, May 06, 2020 to Monday, July 13, 2020

​Dominion Boulevard will be closed between E.C. Row Expressway and Northwood Street for sewer work, road construction and hydro pole relocation. Northwood Street will also be closed from Longfellow Avenue to McKay Avenue.

June Liu-Vajko, Tech III Design and Development Engineering (519) 255-6257 x6339 SheaRock Complete road,sewer Complete All 05/06/2020 00:00:00 07/13/2020 00:00:00
Dougall Ave / Ouellette Place Intersection (From Dougall Ave to Ouellette Place) 8/24/2020 8/26/2020 Monday, August 24, 2020 to Wednesday, August 26, 2020

​Dougall Avenue from the Dougall Avenue/Ouellette Place Intersection up to Eugenie Street, including the northbound left turn lane will be closed for 3 days beginning today from 7:00am to 5:00pm. Access to businesses will remain open to local traffic.

Monday, August 24 to Wednesday, August 26, 2020.

Traffic on Dougall Avenue from E.C. Row Expressway to Ouellette Place will be restricted to one lane in both directions.

Paul Mourad, P. Eng, Project Administrator (519)562-2448 Sterling Ridge Infrastructure Complete road Complete All 08/24/2020 00:00:00 08/26/2020 00:00:00
Dougall Avenue (From Erie Street to Ellis Street) 3/12/2020 6/19/2020 Thursday, March 12, 2020 to Friday, June 19, 2020

​The Windsor Utilities Commission will be reconstructing the watermain on: Dougall Avenue from Erie Street to Ellis Street.

Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 To be determined. Complete watermain Complete All 03/12/2020 00:00:00 06/19/2020 00:00:00
Dougall Avenue / CN Rail Underpass and Multi-Use Trail Project (From Ouellette Place to South Cameron) 3/12/2020 5/29/2020 Thursday, March 12, 2020 to Friday, May 29, 2020
  • A long term closure of the southbound right lane on Dougall Avenue between Dougall Avenue/Ouellette Place and South Cameron Boulevard.
  • Southbound right lane will be closed on Dougall Avenue between Dougall Avenue/Ouellette Place intersection and South Cameron Boulevard. Eastbound South Cameron Boulevard will be closed between Northwood Street and Dougall Avenue. Traffic will be detoured via Northwood Avenue to Dominion Boulevard. Westbound South Cameron will remain open from Dougall to Northwood. Southbound Dougall Avenue will have a lane reduction between South Cameron Boulevard and E.C. Row Expressway, but access to westbound E.C. Row Expressway will remain open. Monday, April 20 at 7:00am to 5:30pm on Friday, May 29, 2020.
  • Southbound Dougall Avenue will have a short-term lane closure between the Dougall Avenue/Ouellette Place intersection and South Cameron Boulevard for additional concrete and railing work. on Tuesday, June 9, 2020 from 7:00am to 2:00pm.
Paul Mourad, P. Eng., Project Administrator (519) 255-6100 x6119 Amico Infrastructures Complete road,railroad Complete All 03/12/2020 00:00:00 05/29/2020 00:00:00
Dougall Avenue and Cabana Road West Intersection (From Dougall Avenue to Cabana Road West) 7/6/2020 9/18/2020 Monday, July 06, 2020 to Friday, September 18, 2020

​The intersection of Dougall Avenue and Cabana Road West will be reduced to one lane in all directions for installation of new Bell manhole and concrete conduit. Only through traffic and right turns will be allowed. Please see Transit Windsor for updated bus route information.

Jane He, P. Eng., Engineering (519) 255-6257 x6358 Aecon Utilities Complete road,bridge Complete All 07/06/2020 00:00:00 09/18/2020 00:00:00
Dufferin Place, Shepherd Street, Hanna Street East (From see description to see description) 9/29/2020 11/27/2020 Tuesday, September 29, 2020 to Friday, November 27, 2020

​The Windsor Utilities Commission will be reconstructing the watermains on:

Dufferin Place from Shepherd Street East to Tecumseh Road (Ward 3)

Shepherd Street East from Ouellette Avenue to Windsor Avenue (Ward 3)

Hanna Street East from Dufferin Place to Windsor Avenue (Ward 3)

 2020-017 Dufferin Hanna Shepherd Pre-Construction Letter.pdf2020-017 Dufferin Hanna Shepherd Pre-Construction Letter.pdf

Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 D'Amore Construction Current watermain,road Current All 09/29/2020 00:00:00 11/27/2020 00:00:00
E.C. Row Expressway (From Huron Church Road to Conservation Drive) 8/4/2020 10/28/2020 Tuesday, August 04, 2020 to Wednesday, October 28, 2020

​Westbound E.C. Row Expressway between Dougall Avenue and Dominion Boulevard will be reconstructed.

Phase 4: Westbound E.C. Row Expressway from Conservation Drive to Huron Church Road will be reduced to one lane starting Tuesday October 20. Weather permitting. ALL RAMPS OPEN.

Eastbound E.C. Row Expressway between Huron Church Road and Conservation Drive will continue to be reduced to one lane of traffic for construction work. All ramps will remain open.

Project completion October 28, 2020.

Michael Cappucci, Contracts Coordinator 519-255-6560 x4234 Coco Paving Current road Current All 08/04/2020 00:00:00 10/28/2020 00:00:00
E.C. Row Expressway Collector Road (From Walker Road to Central Avenue) 8/11/2020 10/12/2020 Tuesday, August 11, 2020 to Monday, October 12, 2020

​The Eastbound collector road between Walker Road and Central Avenue will be closed to all traffic for reconstruction of the CN Railway Bridge. A posted detour route will be in place.

Zoran Savic, Contracts Supervisor Operations (519) 255-6560 x4231 Bridge Contractor - Front Construction, Road, Mil and Pave Contractor - Mill Am Complete bridge,road Complete All 08/11/2020 00:00:00 10/12/2020 00:00:00
E.C. Row Expressway Eastbound (From Walker Road to Central Avenue) 8/11/2020 9/28/2020 Tuesday, August 11, 2020 to Monday, September 28, 2020

​The E.C. Row Expressway Eastbound Collector Road will be closed to all traffic between Walker Road and Central Avenue as part of the rehabilitation of the bridge over CN Rail. A detour for northbound and southbound Central Avenue access will be posted. The E.C. Row Eastbound Central off ramp will remain open. On Tuesday, August 11 to September 28, 2020.

Michael Cappucci, P. Eng. Contracts Coordinator (519) 255-6560 x4234 Front Construction Industries Inc. Complete bridge,road Complete All 08/11/2020 00:00:00 09/28/2020 00:00:00
E.C. Row Expressway Eastbound (From Huron Church Road to Conservation Drive) 8/4/2020 8/19/2020 Tuesday, August 04, 2020 to Wednesday, August 19, 2020

​Eastbound E.C. Row Expressway will be reduced to one lane between Huron Church Road and Conservation Drive for shoulder work. This is being done in preparation for the complete reconstruction of the westbound lanes of E.C. Row Expressway between Dominion Boulevard and Dougall Avenue. All exists will remain open. From 7:00am to 5:00pm daily.

Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 Coco Paving Inc. Complete road Complete All 08/04/2020 00:00:00 08/19/2020 00:00:00
E.C. Row Expressway mill and pave (From Central Avenue to Jefferson Boulevard) 6/29/2020 8/4/2020 Monday, June 29, 2020 to Tuesday, August 04, 2020

Date: weather depending, work will begin June 29th on the westbound lanes.  Eastbound lane construction will begin July 16th 

Duration: weather depending , westbound lane construction will finish July 16th . Eastbound lane work will finish August 4th . NOTE: ALL WORK TO BE COMPLETED BETWEEN THE HOURS OF 8PM AND 6AM
 
Location:
1ST PART OF CONSTRUCTION (WESTBOUND)
The mill and pave operation will begin in both the westbound lanes of EC row between Central and Jefferson.  During the night time hours (8PM-6AM) EC ROW WILL BE CLOSED FROM LAUZON ROAD TO CENTRAL. Detour routes will be in place. 
·   Vehicles will be required to exit at Lauzon road, and follow the detour to Central.  (shown on attached drawing)
·   Vehicles trying to access EC Row from Lauzon will be required to take the detour to Central.  (shown on attached drawing)
·   Vehicles trying to access EC Row from Jefferson will also be required to take the detour to Central.  (shown on attached drawing)
·   Vehicles will be able to access EC Row at Central (where detour ends)
 
2nd PART OF CONSTRUCTION (EASTBOUND)
Both the eastbound lanes of EC row between Central and Jefferson will be milled and paved.  During the night time hours (8PM-6AM) EC ROW WILL BE CLOSED FROM CENTRAL TO LAUZON. Detour routes will be in place. 
·   Vehicles will be required to exit at Central Avenue, and follow the detour to Lauzon.  (shown on attached drawing)
·   Vehicles trying to access EC Row from Central will be required to take the detour to Lauzon.  (shown on attached drawing)
·   Vehicles will be able to access EC Row at Lauzon (where detour ends)
 

 

Michael Cappucci, P. Eng. Contracts Coordinator (519) 255-6560 x4234 Coco Paving Complete road Complete All 06/29/2020 00:00:00 08/04/2020 00:00:00
Foch, Mercer, Highland, Lens (See Description) 3/4/2020 9/25/2020 Wednesday, March 04, 2020 to Friday, September 25, 2020

​The Windsor Utilities Commission will be reconstructing the watermains on: Foch Avenue from McDougall Street to Howard Avenue, Mercer Street from Lens Avenue (Alley) to Logan Avenue, Highland Avenue from Lens Avenue (Alley) to Logan Avenue and Lens Avenue (Alley) from McDougall Street to Howard Avenue. The entire project should take approximately 24 weeks to complete. Project timing is weather dependent.

2020-005 Mercer Highland Foch Lens PH2 Pre-Construction Letter.pdf2020-005 Mercer Highland Foch Lens PH2 Pre-Construction Letter.pdf

Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 D'Amore Construction 2000 Ltd. Complete watermain Complete All 03/04/2020 00:00:00 09/25/2020 00:00:00
Francois Road (From Seminole Street to Alice Street) 5/11/2020 10/23/2020 Monday, May 11, 2020 to Friday, October 23, 2020

​Francois Road will be closed for sewer, pavement, watermain and streetlighting reconstruction. The intersection at Francois Street and Seminole Street will be closed for approximately 2 days starting on Monday May 11, 2020. Local Traffic Only. Reconstruction work will also take place on Reginald Street from Bernard Road to Ellrose Avenue and on Alice Street from Bernard Road to Ellrose Avenue. 

Joe Bressan, Engineering 1 ,Operations (519) 255-6560 x6890 Sterling Ridge Infrastructures Inc. Complete road,sewer,watermain Complete All 05/11/2020 00:00:00 10/23/2020 00:00:00
Grand Marais Road West (From Dougall Avenue to Dominion Boulevard) 7/15/2020 11/23/2020 Wednesday, July 15, 2020 to Monday, November 23, 2020

Grand Marais Road West will be closed for reconstruction.

 

Michael Cappucci, 519-255-6560 Ext 4234 TBD Current road Current All 07/15/2020 00:00:00 11/23/2020 00:00:00
Hall Avenue (From Tecumseh Road East to Hanna Street East) 6/29/2020 6/29/2020 Monday, June 29, 2020

Hall Avenue from Tecumseh Road to Hanna Street will be closed for paving.

 

Michael Cappucci, Public Works 519-255-6560 Ext 4234 Mill-Am Corporation Complete road Complete All 06/29/2020 00:00:00 06/29/2020 00:00:00
Highland Avenue (From Tecumseh Road East to Hanna Street East) 6/3/2020 9/25/2020 Wednesday, June 03, 2020 to Friday, September 25, 2020

The ​​Windsor Utilities Commission will be installing a new 200mm dia. PVC watermain on Highland Avenue from Tecumseh Road East to Hanna Street East. This is the fourth phase of a larger project that has already commenced in the area.

Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 D'Amore Construction (2000) Ltd. Complete watermain Complete All 06/03/2020 00:00:00 09/25/2020 00:00:00
Howard Avenue (From Tecumseh Road East to Lens Avenue) 5/5/2020 7/31/2020 Tuesday, May 05, 2020 to Friday, July 31, 2020

​As part of an ongoing infrastructure renewal program, the Windsor Utilities Commission (WUC) will be installing a new 300mm dia. PVC watermain on Howard Avenue between Tecumseh and Lens. This is the fourth phase of a larger project that includes work on Mercer and Highland between Foch and Tecumseh as well as Logan, Hyde and Irvine.

2020-005 Howard PH1B Pre-Construction Letter.pdf2020-005 Howard PH1B Pre-Construction Letter.pdf

Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 D'Amore Construction (2000) Ltd. Complete watermain Complete All 05/05/2020 00:00:00 07/31/2020 00:00:00
Huron Church Road (From Malden Road to Pool Avenue) 3/23/2020 9/11/2020 Monday, March 23, 2020 to Friday, September 11, 2020

Another section of Huron Church road is set to receive important infrastructure upgrades, including new concrete, curbs, sidewalks, medians and street lighting, between Malden Road and Pool Avenue.

The 4.83 million dollar reconstruction project is possible thanks to 3 million dollars in funding from the provincial government under the Connecting Links Program. The City will contribute the remaining funds.
 
Drivers will see the complete closure of the north bound lanes of the roadway, shifting all traffic to the south bound lanes where two way traffic will be installed.  Once that construction is complete, traffic will shift to the other side, again with one lane of traffic allowed in each direction. During construction, no left turns off Huron Church Road will be permitted through the construction zone.  
 
Access to all businesses will remain open and information has been distributed to businesses and residents along the route, the Ontario Trucking Association as well as FCA (Fiat Chrysler Automobiles).  Road signage will be in place two weeks prior to the start of construction. 
 
Huron church Road will have a brief series of intermitten closures, up to 10 minutes each in duration between Malden Road and Industrial Drive. During these short closures, traffic in the construction zone will be stopped in both directions by flag persons. This will allow a crane to remove the overhead sign structure at Pool Avenue. All efforts will be made to minimize the duration of the closures, but some delays can be expercted. On Saturday, May 2, 2020 from 7:00am to 12:00pm (weather permitting).
Dwayne Dawson, Executive Director of Operations (519) 255-6415 Pierascenzi Construction Limited Complete curb,road,sidewalk Complete All 03/23/2020 00:00:00 09/11/2020 00:00:00
Huron Church Road (From Tecumseh Road West to College Avenue) 8/24/2020 8/28/2020 Monday, August 24, 2020 to Friday, August 28, 2020

​Huron Church Road will have moving single lane closures for geotechnical investigation work from Tecumseh Road West to College Avenue.

Zoran Savic, Contracts Supervisor Operations (519) 255-6560 x4231 EXP Services Inc. Complete road Complete All 08/24/2020 00:00:00 08/28/2020 00:00:00
Langlois Avenue (From Erie Street East to Giles Boulevard East) 2/24/2020 5/29/2020 Monday, February 24, 2020 to Friday, May 29, 2020

​As part of an ongoing infrastructure renewal program, the Windsor Utilities Commission (WUC) will be installing a new 200mm Dia. PVC watermain on Langlois Avenue between Erie Street East and Giles Boulevard East.

2020-004 Langlois Pre-Construction Letter.pdf2020-004 Langlois Pre-Construction Letter.pdf

Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 Coco Paving Complete watermain Complete All 02/24/2020 00:00:00 05/29/2020 00:00:00
Lincoln Road (From Niagara Street to Ottawa Street) 5/18/2020 8/28/2020 Monday, May 18, 2020 to Friday, August 28, 2020

​The Windsor Utilities Commission will be installing a new 200mm dia. PVC watermain on Lincoln Road between Niagara Street and Ottawa Street.

2020-016 Lincoln Pre-Construction Letter.pdf2020-016 Lincoln Pre-Construction Letter.pdf

Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 Coco Paving Complete watermain Complete All 05/18/2020 00:00:00 08/28/2020 00:00:00
Lincoln Road (From Assumption Street to Wyandotte Street East) 6/10/2020 8/25/2020 Wednesday, June 10, 2020 to Tuesday, August 25, 2020

​Lincoln Road is closed between Assumption Street and Wyandotte Street East for watermain and road reconstruction. Local traffic only.

Michael Cappucci, P. Eng. Contracts Coordinator (519) 255-6560 x4234 D'Amore Construction Complete road,watermain Complete All 06/10/2020 00:00:00 08/25/2020 00:00:00
Lincoln Road (From Richmond Street to Ontario Street) 10/7/2020 10/7/2020 Wednesday, October 07, 2020

​Lincoln Road has lane closures between Richmond Street and Ontario Street for manhole repair work. Flag persons are present.

Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 BXF Infrastructures Inc. Complete road Complete All 10/07/2020 00:00:00 10/07/2020 00:00:00
Logan Avenue, Mercer Street, Highland Avenue, Hyde Avenue, Joffre Place (See Description) 3/30/2020 10/16/2020 Monday, March 30, 2020 to Friday, October 16, 2020

​As part of an ongoing infrastructure renewal program, the Windsor Utilities Commission (WUC) will be installing a new 200mm Dia. watermain on Mercer Street between Logan and Tecumseh, on Highland Avenue between Logan and Tecumseh, on Logan Avenue between McDougall and Howard on Hyde Avenue between Howard and the cul-de-sac and on Joffre Place between Mercer and the cul-de-sac.

2020-005 Mercer Highland Foch Lens PH3 Pre-Construction Letter.pdf2020-005 Mercer Highland Foch Lens PH3 Pre-Construction Letter.pdf

Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 D'Amore Construction (2000) Ltd. Complete watermain Complete All 03/30/2020 00:00:00 10/16/2020 00:00:00
Louis Avenue (From Erie Street to Cataraqui Street) 9/9/2019 12/13/2019 Monday, September 09, 2019 to Friday, December 13, 2019

Louis Avenue will be closed for road and watermain construction​.

WS.0475 Louis Pre-Construction Letter.pdfWS.0475 Louis Pre-Construction Letter.pdf

Phong Nguy, 519-255-6560 Ext 4253 Sterling Ridge Infrastructures Complete road,watermain Complete All 09/09/2019 00:00:00 12/13/2019 00:00:00
Malden Road (From Huron Church Road to Daytona Avenue) 10/19/2020 11/6/2020 Monday, October 19, 2020 to Friday, November 06, 2020

​Malden Road will be closed between Huron Church Road and Daytona Avenue for road reconstruction. From Monday, October 19 to Friday, November 6, 2020. (weather permitting).

Michael Cappucci, P. Eng. Contracts Coordinator (519) 255-6326 Pierascenzi Construction Limited Current road Current All 10/19/2020 00:00:00 11/06/2020 00:00:00
Malden Road/Daytona Avenue Intersection (From Malden Road to Daytona Avenue) 10/5/2020 10/30/2020 Monday, October 05, 2020 to Friday, October 30, 2020

​Upcoming reconstruction work on the intersection at Malden Road and Daytona Avenue Intersection will affect traffic in the area as follows:

Phase 1 - Daytona Avenue closed to through traffic. Malden Road between Huron Church Road and Daytona Avenue will be closed to through traffic. Access will be permitted to area businesses.

Phase 2 - Daytona Avenue open to north-south traffic only. Malden Road will be closed to all traffic between Huron Church Road and Daytona Avenue.

Monday, October 5 to Friday, October 23, 2020.

Phase 1 - October 5 to October 15 (weather permitting)

Phase 2 - October 16 to October 23 (weather permitting)

Michael Cappucci, P. Eng. Contracts Coordinator (519) 255-6326 Pierascenzi Construction Limited Current road Current All 10/05/2020 00:00:00 10/30/2020 00:00:00
Marentette Avenue and Irvine Avenue (From Tecumseh Road East to Howard Avenue) 3/18/2020 9/4/2020 Wednesday, March 18, 2020 to Friday, September 04, 2020

The Windsor Utilities Commission will be reconstructing the watermains on: Marentette Avenue from Tecumseh Road East to Irvine Avenue (ward 4) and on Irvine Avenue from Marentette Avenue to Howard Avenue (ward 4).

2020-005 Marentette Irvine PH1A Pre-Construction Letterr.pdf2020-005 Marentette Irvine PH1A Pre-Construction Letterr.pdf

Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 D'Amore Construction (2000) Ltd. Complete watermain Complete All 03/18/2020 00:00:00 09/04/2020 00:00:00
Marentette Avenue and Langlois Avenue (From E.C. Row Avenue to Sydney Avenue to E.C. Row Avenue to North Service Road) 11/4/2019 12/13/2019 Monday, November 04, 2019 to Friday, December 13, 2019

​Marentette Avenue from E.C. Row Avenue to Sydney Avenue

Langlois Avenue from E.C. Row Avenue to North Service Road (crossing under E.C. Row Expressway)

Spencer Johnston, Supervisor, Water Construction & Design (519) 251-7300 x609 To be determined. Complete watermain Complete All 11/04/2019 00:00:00 12/13/2019 00:00:00
Marion Avenue (From Cataraqui Street to Giles Boulevard East) 7/13/2020 11/6/2020 Monday, July 13, 2020 to Friday, November 06, 2020

​Marion Avenue from Cataraqui Street to Giles Boulevard East will be closed for watermain and road reconstruction.

Michael Cappucci, P. Eng. Contracts Coordinator (519) 255-6560 x4234 Sterling Ridge Infrastructure Inc. Current road,watermain Current All 07/13/2020 00:00:00 11/06/2020 00:00:00
McHugh Street (From Cypress Avenue to Florence Avenue) 12/9/2019 2/1/2020 Monday, December 09, 2019 to Saturday, February 01, 2020

​McHugh Street from Cypress Avenue to Florence Avenue will be closed for the installation of a new trunk storm sewer. Lane reductions and periodic intersection closures as posted.

Pat Winters, P. Eng. (519) 255-6257 x6462 Major Construction 2010 Complete sewer Complete All 12/09/2019 00:00:00 02/01/2020 00:00:00
Norman Road (From Tecumseh Road East to Adstoll Avenue) 6/15/2020 9/3/2020 Monday, June 15, 2020 to Thursday, September 03, 2020

​Norman Road is closed for sewer, pavement, watermain and street lighting reconstruction. Local Traffic Only.

Janelle Coombs, P. Eng. Engineering II (519) 255-6257 x6407 SheaRock Construction Group Inc. Complete road,sewer,watermain Complete All 06/15/2020 00:00:00 09/03/2020 00:00:00
Olive Road (From Seminole Street to Milloy Street) 6/24/2019 12/6/2019 Monday, June 24, 2019 to Friday, December 06, 2019

​Olive Road from Seminole Street to Milloy Street will be closed for sewer, watermain and road reconstruction. Reginald Street to Norman Road will be closed for road reconstruction.

Olive 38-19 - Sidewalk Notice to Homeowners.pdfOlive 38-19 - Sidewalk Notice to Homeowners.pdf

Olive Road 38-19 - Project Notification - Works Postponed.pdfOlive Road 38-19 - Project Notification - Works Postponed.pdf

June Liu-Vajko Technologist III (519) 255-6257 x6339 Sterling Ridge Infrastructure Inc. Complete road,sewer,watermain Complete All 06/24/2019 00:00:00 12/06/2019 00:00:00
Parent Avenue and Hanna Street East (From see description to see description) 10/13/2020 12/18/2020 Tuesday, October 13, 2020 to Friday, December 18, 2020

​The Windsor Utilities Commission will be reconstructing the watermains on:

Parent Avenue - Giles Boulevard to Tecumseh Road East (Ward 4)

Hanna Street East - Elsmere Avenue to Langlois Avenue

WUC Contract 2020-032 Parent - Tecumseh to Giles.pdfWUC Contract 2020-032 Parent - Tecumseh to Giles.pdf

Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 Coco Paving Current watermain Current All 10/13/2020 00:00:00 12/18/2020 00:00:00
Park Street West (From Pelisser Street to Caron Avenue) 8/6/2019 11/15/2019 Tuesday, August 06, 2019 to Friday, November 15, 2019

Park Street West will be closed for road and watermain reconstruction​.

City Contract 09-19 Park Street - Construction Notice.pdfCity Contract 09-19 Park Street - Construction Notice.pdf

Mike Abaldo, P. Eng., (519) 255-6560 x4332 Major Construction Complete road,watermain Complete All 08/06/2019 00:00:00 11/15/2019 00:00:00
Patricia Road and Vista Place (From Riverside Drive West to University Avenue West) 5/21/2020 7/31/2020 Thursday, May 21, 2020 to Friday, July 31, 2020

​Patricia Road and Vista Place from Riverside Drive West to University Avenue West will be closed for watermain and road reconstruction. Follow posted detour signs.

Michael Cappucci, P. Eng. Contracts Coordinator (519) 255-6560 x4234 D'Amore Construction Complete road,watermain Complete All 05/21/2020 00:00:00 07/31/2020 00:00:00
Pillette Road (From Seminole Street to South National) 11/20/2019 11/22/2019 Wednesday, November 20, 2019 to Friday, November 22, 2019

​Pillette Road will be closed between Seminole Street and South National Street for restoration work. The road will be re-open each evening. Local traffic only. On Wednesday November 20, Thursday November 21 and Friday November 22 from 7:00am to 7:00pm.

Sergio Colucci, Eng. II, City of Windsor (519) 255 6100 x 6336 D'Amore Construction Complete road,sewer,watermain Complete All 11/20/2019 00:00:00 11/22/2019 00:00:00
Provincial/Division Corridor Improvements Phase 2 (From Provincial Road to Legacy Park Drive) 10/20/2020 11/2/2020 Tuesday, October 20, 2020 to Monday, November 02, 2020

​Provincial Road from Lowe's / Monach Basics intersection to Legacy Park Drive will have lane restrictions for watermain work. Flag persons will be present.

Jane He, P. Eng., Engineering (519) 255-6257 x3658 J&J Lepera Infrastructure Current watermain Current All 10/20/2020 00:00:00 11/02/2020 00:00:00
Randolph Avenue (From Riverside Drive West to University Avenue West) 5/20/2020 7/31/2020 Wednesday, May 20, 2020 to Friday, July 31, 2020

​Randolph Avenue will be closed for watermain and road reconstruction from Riverside Drive West to University Avenue West.

Michael Cappucci, P. Eng. Contracts Coordinator (519) 255-6560 x4234 D'Amore Construction Complete road,watermain Complete All 05/20/2020 00:00:00 07/31/2020 00:00:00
Rhodes Drive Multi-Use Trail Phase 1 (From see description to see description) 3/31/2020 6/29/2020 Tuesday, March 31, 2020 to Monday, June 29, 2020

​Construction of a Multi-Use Trail on Rhodes Drive from Kautex Drive and Deziel Drive to Jefferson Boulevard and Quality Way.

Juan Paramo, P. Eng. City of Windsor 519-999-6378 Nevan Construction Complete None. Complete All 03/31/2020 00:00:00 06/29/2020 00:00:00
Rhodes Drive Multi-Use Trail Phase 2 (From Pilltette Road to Jefferson Boulevard) 7/20/2020 10/26/2020 Monday, July 20, 2020 to Monday, October 26, 2020

A bicycle path will be constructed along the North side of Rhodes Drive between Pillette Road to Jefferson Boulevard and along the West side of Jefferson Boulevard between Rhodes Drive to Quality Way.

Juan Paramo P.Eng. To be determined. Complete None. Complete All 07/20/2020 00:00:00 10/26/2020 00:00:00
Riverside Drive East (From Belleview Avenue to Cadillac Street) 9/30/2020 9/30/2020 Wednesday, September 30, 2020

​Riverside Drive East will have lane restrictions between Belleview Avenue and Cadillac Street for manhole repair work. Flag persons will be present. From 8:00am to 5:00pm on Wednesday, September 30, 2020.

Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 BXF Infrastructures Inc. Complete road Complete All 09/30/2020 00:00:00 09/30/2020 00:00:00
Riverside Drive East (From Montreuil Avenue to Drouillard Road) 10/7/2020 10/7/2020 Wednesday, October 07, 2020

​Riverside Drive East will have lane closures between Montreuil Avenue and Drouillard Road for manhole repair work.

Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 BXF Infrastructures Inc. Complete road Complete All 10/07/2020 00:00:00 10/07/2020 00:00:00
Riverside Drive East at Devonshire Road (From Riverside Drive East to Devonshire Road) 6/30/2020 7/25/2020 Tuesday, June 30, 2020 to Saturday, July 25, 2020

​Riverside Drive East at Devonshire Road will experience lane reductions. Traffic will be maintained in both directions for the majority of the project, except during surface asphalt operations which is scheduled for July 25, 2020. The right turn lane from Riverside Drive to Devonshire Road southbound will be closed.

Paul Mourad, P. Eng. (519) 562-2448 Pierascenzi Construction Limited Complete road Complete All 06/30/2020 00:00:00 07/25/2020 00:00:00
Riverside Drive East at Strabane Avenue (From Pratt Place to George Avenue) 10/20/2020 12/18/2020 Tuesday, October 20, 2020 to Friday, December 18, 2020

​Riverside Drive East will be reduced to one lane in each direction between Pratt Place and George Avenue for sewer and road construction, and Strabane Avenue will be closed (only local traffic allowed) from Riverside Drive East to Wyandotte Street East.

June Liu-Vajko, Tech III Design and Development Engineering (519) 255-6257 x6339 Sherway Contracting (Windsor) Limited Current road,sewer Current All 10/20/2020 00:00:00 12/18/2020 00:00:00
Riverside Drive West (From Patricia Road to Huron Church Road) 5/21/2020 7/31/2020 Thursday, May 21, 2020 to Friday, July 31, 2020

​Riverside Drive West from Patricia Road to Huron Church Road will be closed for watermain and road reconstruction. Follow posted detour signs.

Michael Cappucci, P. Eng. Contracts Coordinator (519) 255-6560 x4234 D'Amore Construction Complete road,watermain Complete All 05/21/2020 00:00:00 07/31/2020 00:00:00
Sandwich Street Roundabout (see description) 8/20/2020 8/21/2020 Thursday, August 20, 2020 to Friday, August 21, 2020

​Road work in the area of Sandwich Street Roundabout will require some closures this Thursday and Friday.

From 7:00am to 4:00pm, Thursday, August 20, 2020 and from 7:00am to 1:00pm Friday, August 21, 2020, the following closures will be in effect:

  • Riverside Drive West and University Avenue West will both be closed west of Huron Church Road.
  • Sandwich Street will be closed east of Mill Street.
  • Rosedale Avenue will be closed north of Peter Street.

Detours will be posted.

Michael Cappucci, P. Eng. Contracts Coordinator (519) 255-6560 x4234 Coco Paving Inc. Complete road Complete All 08/20/2020 00:00:00 08/21/2020 00:00:00
Special Events (Details pending) 5/26/2020 1/1/2021 Tuesday, May 26, 2020 to Friday, January 01, 2021

​The request from Downtown Windsor Business Improvement Association to temporarily close Pelissier Street between Park Street West and Wyandotte Street West, and Maiden Lane between Ouellette Avenue and Pelissier Street to host the regular Downtown Windsor Farmers Market every Saturday between May 30, 2020 and October 31, 2020 between the hours of 7:00am - 2:00pm.

Office of the City Clerk Council Services (519) 255-6211 N/A Current special event Current All 05/26/2020 00:00:00 01/01/2021 00:00:00
Tranby Avenue (From Isabelle Place to Parkview Avenue) 7/28/2020 10/31/2020 Tuesday, July 28, 2020 to Saturday, October 31, 2020

Tranby Avenue from Isabelle Place to Parkview Avenue will be closed.

Tiffany Pocock, Eng. III Coco Paving Inc. Current road,sewer,watermain Current All 07/28/2020 00:00:00 10/31/2020 00:00:00
Walker Road (From Digby Street to Parkdale Avenue) 9/29/2020 9/30/2020 Tuesday, September 29, 2020 to Wednesday, September 30, 2020

​Southbound Walker Road will have a lane reduction between Digby Street and Parkdale Avenue for sewer repair. Flag people will be present. From 8:00am to 4:00pm on Tuesday, September 29 and Wednesday, September 30, 2020.

Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 DanRuss Contracting Inc. Complete sewer Complete All 09/29/2020 00:00:00 09/30/2020 00:00:00
Westbound Tecumseh Road East (From Lauzon Parkway to Jefferson Boulevard) 9/14/2020 9/28/2020 Monday, September 14, 2020 to Monday, September 28, 2020

​Westbound Tecumseh Road East will have lane reductions between Lauzon Parkway and Jefferson Boulevard for road repair work.

Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 Villa Construction Complete road Complete All 09/14/2020 00:00:00 09/28/2020 00:00:00
Wyandotte Street East (From Janisse Drive to St Rose Avenue) 9/3/2019 10/25/2019 Tuesday, September 03, 2019 to Friday, October 25, 2019

Wyandotte Street East will be reduce to one lane in each direction for pavement rehabilitation.

Letter to Residents - Wyandotte E.pdfLetter to Residents - Wyandotte E.pdf

 

Phong Nguy, 519-255-6560 Ext 4253 Pierascenzi construction Limited Complete road Complete All 09/03/2019 00:00:00 10/25/2019 00:00:00

Projects Under Construction

For information on projects currently under construction, click here to launch the Construction and Detours mapping application

Projects Scheduled for Construction

For information on sewers, road widening, street lighting, City-owned facilities, and new subdivisions scheduled for construction in the near future, use the database above.  For descriptions of some maintenance activities, please consult the following pages:

Building Windsor's Future

The City of Windsor will undergo a physical transformation over the coming years due to a significant investment in capital projects. For a detailed list of current projects please visit  the Building Windsor's Future page. 

Engineering Requirements for Development in the Public Right-of-Way

For information on the City's engineering standards for construction works within the public right of way, please consult the Public Infrastructure & Right-of-Way Requirements page.

Engineering Department
350 City Hall Square West, 3rd Floor
P. O. Box 1607
Windsor, Ontario
Canada
N9A 6S1

Phone: For general information, call 311. For detailed inquires, call 519-255-6257.
Fax: 519-255-9847
Email: engineeringdept@citywindsor.ca

​​​

 

​ ​​​​​​