4th Street (From Continental Avenue to Dead end) |
10/2/2023 |
11/10/2023 |
Monday, October 02, 2023 to Friday, November 10, 2023 |
As part of an ongoing infrastructure renewal program, the Windsor Utilities Commission (WUC) will be installing a new 150mm PVC watermain on 4th Street from Continental southerly to the dead end.
Beginning week of October 2nd to November 10, 2023
|
Spencer Johnston, Manager Water Constructiion & Design, Enwin Utilities Ltd., 519-251-7300 ext. 609, cell #519-791-7090 |
D'Amore Construction (2000) Ltd. |
Complete |
watermain |
Complete All |
10/02/2023 00:00:00 |
11/10/2023 00:00:00 |
Albert Road (From Seminole Street to Metcalfe Street) |
6/19/2023 |
11/3/2023 |
Monday, June 19, 2023 to Friday, November 03, 2023 |
Albert Road from Seminole Street to Metcalfe Street, Metcalfe Street from the dead end to the Alley east of Albert Road and the alley (between Albert Road and St. Luke Road) from Metcalfe Street to 25m south will be closed for approximately 4 months for sewer, pavement, watermain and street lighting rehabilitation. Local traffic will be permitted only. The westbound lane of Seminole Street will be shifted around the area of construction at the intersection of Albert Road and Seminole Street as needed.
|
Joe Bressan, EIT Engineering 1, Operations (519) 255-6100 x6890 |
Sherway Contracting (Windsor) Limited |
Complete |
road,sewer,watermain |
Complete All |
06/19/2023 00:00:00 |
11/03/2023 00:00:00 |
Aubin Road (From Alice Street to Guy Street) |
7/31/2023 |
12/14/2023 |
Monday, July 31, 2023 to Thursday, December 14, 2023 |
Aubin Road from Alice Street to Guy Street will be closed for apporximately 4 months for sewer, pavement, watermain, and street lighting rehabilitation. Local traffic will be permitted only.
July 31st, 2023 to December 14th, 2023-Weather permitting
|
Juan Florian, EIT Engineer I, Public Works-Operations, 519-255-6560 ext.4233 |
SheaRock Construction Group Inc., |
Complete |
watermain,sewer,road,curb |
Complete All |
07/31/2023 00:00:00 |
12/14/2023 00:00:00 |
Banwell Road (From Palmetto Street to Mulberry Drive/Wildwood Drive) |
8/2/2022 |
6/30/2023 |
Tuesday, August 02, 2022 to Friday, June 30, 2023 |
Installation of storm sewers, road widening (including trail and sidewalks), roundabout and streetlights on Banwell Road from Palmetto Street to Mulberry Drive/Wildwood Drive. Alternating traffic lanes. Local traffic only.
The southbound lane on Banwell Road between Palmetto Street and Mulberry/Wildwood Drive will be closed on Thursday, September 1 from 9:00am to 3:00pm and on Friday, September 2 from 9:00am to 2:00pm for streetlight work. Local traffic only.
As part of the Banwell Road improvements, Phase 2, the Wildwood Drive/Banwell Road intersection will be closed to traffic for sewer work. From 7:00am to 5:00pm on Monday, October 3 to Thursday, October 6, 2022.
|
Paul Mourad, P. Eng. (519) 255-6100 x6119 |
SheaRock Construction Group Inc. |
Complete |
sewer,road,sidewalk |
Complete All |
08/02/2022 00:00:00 |
06/30/2023 00:00:00 |
Baseline Road (From 7th Concession Road to 8th Concession Road) |
9/26/2023 |
12/22/2023 |
Tuesday, September 26, 2023 to Friday, December 22, 2023 |
Baseline Road will be closed between 7th Concession Road and 8th Concession Road for sanitary sewer and watermain construction. Local traffic only.
Tuesday, September 26 until Friday, December 22, 2023 (weather permitting)
|
Daniel Lopez, P. Eng. Engineer II, Public Works-Engineering, 519-255-6257 ext. 6402 |
GIP Paving |
Complete |
sewer,watermain |
Complete All |
09/26/2023 00:00:00 |
12/22/2023 00:00:00 |
Baseline Road (From 7th Concession Road to 8th Concession Road) |
3/11/2024 |
3/31/2024 |
Monday, March 11, 2024 to Sunday, March 31, 2024 |
Baseline Road will be closed between 7th Concession Road and 8th Concession Road for watermain construction and surface restoration.
Local traffic only.
Monday, March 11, until Sunday, March 31, 2024 (weather permitting)
51-23 Baseline - Resuming Construction Notice Letter (FM).pdf |
Daniel Lopez, P. Eng. Engineer II, Public Works-Engineering, 519-255-6257 ext. 6402 |
Green Infrastructure Partners (GIP) Paving Inc. |
Current |
watermain,road |
Current All |
03/11/2024 00:00:00 |
03/31/2024 00:00:00 |
Brock Street (From Sandiwch Street to Peter Street) |
8/9/2023 |
8/10/2023 |
Wednesday, August 09, 2023 to Thursday, August 10, 2023 |
Brock Street will be closed from Sandwich Street to Peter Street for road repair. Local traffic only.
7a.m. to 6p.m. Wednesday, August 9, and Thursday, August 10, 2023
|
Roberta Harrison Coordinator, 519-255-6560 x4241 |
DiPonti Paving |
Complete |
road |
Complete All |
08/09/2023 00:00:00 |
08/10/2023 00:00:00 |
Cabana Road Corridor Improvements - Phase 4 (From Mount Carmel Drive to Highway 3) |
4/10/2023 |
12/22/2023 |
Monday, April 10, 2023 to Friday, December 22, 2023 |
Cabana Road West from Mount Carmel Drive to Highway 3 will be under construction for a new storm sewer and isolated sanitary sewer replacements. Road widening to four lanes plus on-road bike lanes with buffer zone, including curb and gutter, sidewalks and street lighting from Dominion Bulevard to Highway 3. Traffic may be intermittently restricted to one lane during the day with flag persons on site. The construction is anticipated to be completed before the end of 2023, weather permitting.
Cabana Road West will be reduced to one lane in each direction between Glenwood Avenue and Charlevoix Avenue as part of Phase 4 of the Cabana Road Corridor Improvements. No left turns will be permitted. Flagging may occur during the construction as needed.
Geraedts Drive will be open by July 19, 2023. Curry Street south of Cabana Road West will be closed from 5pm on July 18, 2023 to August 18, 2023.
Glenwood Avenue will be closed from Cabana Road West to Cherrylawn Crescent (north entrance) for road and sewer construction. From Monday, June 12 until Friday, August 18, 2023.
All access to the St. Calir College site will be from the Highway 3 entrance during this time. Access to the Sport Plex will be maintained during this time of closure, but access to Lot V will not be available due to the closure of Geraedts Drive.
Please follow the detour signage and drive safely.
Commencement of Construction - Tender 151-22 (002).pdf
|
Jane He, P. Eng., Engineering (519) 255-6257 x6358 |
Amico Infrastructures Inc. |
Complete |
curb,road,sewer,sidewalk |
Complete All |
04/10/2023 00:00:00 |
12/22/2023 00:00:00 |
Clemenceau Boulevard (From CNR Tracks to North Service Road East) |
8/28/2023 |
12/8/2023 |
Monday, August 28, 2023 to Friday, December 08, 2023 |
Clemenceau Boulevard will be closed from the CNR Tracks to North Service Road East for storm sewer, curb/gutter improvement, pavement and water main rehabilitation.
Monday, August 28 until Friday, December 8, 2023
|
Joseph Bressan, Engineer I, Engineering, 519-255-6100 ext. 6890 |
SheaRock Construction Group Inc. |
Complete |
sewer,curb,watermain |
Complete All |
08/28/2023 00:00:00 |
12/08/2023 00:00:00 |
Dillon Drive (From Jarvis Avenue to Kennedy Court) |
9/22/2023 |
9/22/2023 |
Friday, September 22, 2023 |
Dillon Drive between Jarvis Avenue and Kennedy Court will be open to local traffic only due to road work (crack sealing).
September 22, 2023, 7:00 a.m. to 7:00 p.m. |
Jaeger King, Engineer I, 519-255-6250 ext. 4314 |
Nasci Construction |
Complete |
road |
Complete All |
09/22/2023 00:00:00 |
09/22/2023 00:00:00 |
Dominion Boulevard (From Northwood Street to Ojibway Street) |
8/9/2023 |
2/2/2024 |
Wednesday, August 09, 2023 to Friday, February 02, 2024 |
Dominion Boulevard, from Northwood Street to Ojibway Street, will be under construction for street lighting rehabilitation work. Construction barrels will be installed to direct traffic through the site.
|
Aojeen Issac, Eng. II, City of Windsor (519) 255-6257 x6368 |
Sterling Ridge Infrastructure Inc. |
Complete |
road,sewer,watermain |
Complete All |
08/09/2023 00:00:00 |
02/02/2024 00:00:00 |
Dominion Boulevard (From Northwood Street to Ojibway Street) |
1/15/2024 |
1/19/2024 |
Monday, January 15, 2024 to Friday, January 19, 2024 |
Dominion Boulevard will have alternating lane restrictions between Northwood Street and Ojibway Street for streetlight construction. The roadway will be accessible; however, construction barrels will be in place to direct traffic through the construction site.
Work will begin in the northbound lane of Dominion Boulevard. Once complete, crews will switch over to the southbound lane. Work will finish at the intersection of Dominion Boulevard and Ojibway Street.
Please follow the detour signage and reduce your speed through the work zone.
Monday, January 15, until Friday, January 26, 2024 |
Aojeen Issac, Engineer II, Engineering Dept., 519-255-6257 ext. 6368 |
Sterling Ridge Infrasturctures Inc./City of Windsor |
Complete |
None. |
Complete All |
01/15/2024 00:00:00 |
01/19/2024 00:00:00 |
Dougall Avenue (From Eugenie Street West to Ouellette Avenue) |
2/26/2024 |
3/15/2024 |
Monday, February 26, 2024 to Friday, March 15, 2024 |
Extended:
Dougall Avenue will have lane restrictions between Eugenie Street West and the Ouellette Place intersection for storm sewer rehabilitation.
Monday, February 26, until Friday, March 15, 2024 (weather permitting) |
Patrick Muzyka, P. Eng. Technologist III, Public Works-Engineering, 519-255-6100, ext. 6472 |
Sherway Contracting (Windsor) Limited |
Complete |
sewer |
Complete All |
02/26/2024 00:00:00 |
03/15/2024 00:00:00 |
E.C. Row Expressway (From Westbound E.C. Row Expressway to Dominion Boulevard) |
7/26/2023 |
7/28/2023 |
Wednesday, July 26, 2023 to Friday, July 28, 2023 |
The westbound E.C. Row Expressway on-ramp at Dominion Boulevard will have lane restricitons for brushing (cutting of brush on roadside)
8 a.m. to 5 p.m., Wednesday, July 26 and Thursday, July 27, 2023 |
Roberta Harrison, Coordinator Maintenance Operations 519-255-6560 ext. 4241 |
Belmont |
Complete |
road |
Complete All |
07/26/2023 00:00:00 |
07/28/2023 00:00:00 |
E.C Row Expressway Off-Ramp (Details pending) |
7/20/2023 |
7/21/2023 |
Thursday, July 20, 2023 to Friday, July 21, 2023 |
The westbound E.C. Row Expressway off-ramp at Central Avenue will be
closed for milling and paving, and westbound expressway traffic will be reduced
to one lane in the area.
From 8 p.m. Thursday, July 20, until 6 a.m. Friday, July 21, 2023
(weather permitting)
|
Charles Hartford Contracts Coordinator Operations 519-255-6560 ext. 4234 |
GIP Paving |
Complete |
road |
Complete All |
07/20/2023 00:00:00 |
07/21/2023 00:00:00 |
E.C. Row Expressway Ramp and Lane Closures (From Lauzon Parkway to Jefferson Boulevard) |
3/9/2021 |
3/9/2021 |
Tuesday, March 09, 2021 |
Ramp and Lane closures on E.C. Row Expressway between Jefferson Boulevard and Lauzon Parkway for guardrail repairs will affect traffic flow.
Closure of eastbound on-ramp at Lauzon Parkway, 9 a.m. to 12 p.m.
Closure of eastbound off-ramp at Lauzon Parkway and northbound lane restrictions, 12 p.m. to 2 p.m.
Westbound lane restrictions between Lauzon Parkway and Jefferson Boulevard, 12 p.m. to 3 p.m. |
Michael Cappucci, Contracts Coordinator 519-255-6326 |
Royal Fence |
Complete |
None. |
Complete All |
03/09/2021 00:00:00 |
03/09/2021 00:00:00 |
Elm Avenue (From Riverside Drive West to Wyandotte Street West) |
10/2/2023 |
12/22/2023 |
Monday, October 02, 2023 to Friday, December 22, 2023 |
As part of an ongoing infrastructure renewal program, the Windsor Utilities Commission (WUC) will be installing a new 200mm PVC watermain on Elm Avenue from Riverside Drive West to Wyandotte Street West.
Beginning week of October 2, 2023 to December 22, 2023
|
Spencer Johnston, Manager Water Constructiion & Design, Enwin Utilities Ltd., 519-251-7300 ext. 609, cell #519-791-7090 |
D'Amore Construction (2000) Ltd. |
Complete |
watermain |
Complete All |
10/02/2023 00:00:00 |
12/22/2023 00:00:00 |
Elsmere Avenue (From Erie Street East to Elliott Street East) |
3/4/2024 |
6/10/2024 |
Monday, March 04, 2024 to Monday, June 10, 2024 |
Elsmere Avenue from Erie Street East to Elliott Street East will be closed for approximately 4 months for sewer, pavement, watermain, and street lighting rehabilitaion. Local traffic will be permitted only.
Week of March 4, 2024 to approximately June 10, 2024 (weather permitting)
Elsmere Ave - Resumed Construction Notice Letter Revision 2 (SL)(FM).pdf
|
Matt Lemmon, EIT, Engineer I, Public Works-Operations, 519-255-6560 ext. 6305 |
Major Construction (2010) Ltd.,Addy Al-Abbas, 519-256-3971 |
Current |
watermain,sewer,road,bridge |
Current All |
03/04/2024 00:00:00 |
06/10/2024 00:00:00 |
George Street and Wyandotte Street East (Details pending) |
8/4/2023 |
8/4/2023 |
Friday, August 04, 2023 |
George Street and Wyandotte Street East will have lane restrictions for sewer work.
8am to 4pm Friday, August 4, 2023 |
Roberta Harrison Coordinator, 519-255-6560 x4241 |
DanRuss |
Complete |
sewer |
Complete All |
08/04/2023 00:00:00 |
08/04/2023 00:00:00 |
Giles Boulevard East (From Parent Avenue to Gladstone Avenue) |
4/10/2023 |
5/26/2023 |
Monday, April 10, 2023 to Friday, May 26, 2023 |
Giles Boulevard East from Gladstone Avenue to Parent Avenue will resume construction for pavement work on the north side (westbound lane).
Giles Boulevard East will be partially closed. The closure of lanes and intersections will depend on the progress of construction and may/may not permit local traffic and side road parking.
Please follow the detour signage and drive safely.
From April 10, 2023 to May 26, 2023.
|
Aojeen Issac, P. Eng. Engineering Department (519) 255-6257 x6368 |
J.C.S. Construction Inc. / City of Windsor |
Complete |
road |
Complete All |
04/10/2023 00:00:00 |
05/26/2023 00:00:00 |
Giles Boulevard East (From Langlois Avenue to Gladstone Avenue) |
11/13/2023 |
11/16/2023 |
Monday, November 13, 2023 to Thursday, November 16, 2023 |
Giles Boulevard East will be closed between Langlois Avenue and Gladstone Avenue for surface asphalt.
Local Traffic Only. |
Charles Hartford, Contracts Coordinator, 519-255-6560 x4234 chartford@citywindsor.ca |
Green Infrastructure Partners |
Complete |
road |
Complete All |
11/13/2023 00:00:00 |
11/16/2023 00:00:00 |
Goyeau Street (From Giles Boulevard East to Ellis Street East) |
8/9/2023 |
10/6/2023 |
Wednesday, August 09, 2023 to Friday, October 06, 2023 |
Goyeau Street from Giles Boulevard East to Ellis Street East will be closed for Watermain and Road Reconstruction. Local traffic only.
|
Charles Hartford, Contracts Coordinator, (519) 255-6560 x4234 |
Nevan Construction |
Complete |
watermain,road |
Complete All |
08/09/2023 00:00:00 |
10/06/2023 00:00:00 |
Goyeau Street Lane Closure (From Elliott Street East to Erie Street East) |
10/4/2023 |
12/1/2023 |
Wednesday, October 04, 2023 to Friday, December 01, 2023 |
Northbound Goyeau Street will be closed between Elliott Street East and Erie Street East for water main repair and road rehabilitation. Southbound Goyeau Street will be open for local traffic only through the construction zone.
|
Charles Hartford |
Nevan Construction |
Complete |
road,watermain |
Complete All |
10/04/2023 00:00:00 |
12/01/2023 00:00:00 |
Highway 3 (From Highway 3 to Cabana Road West) |
12/7/2023 |
12/7/2023 |
Thursday, December 07, 2023 |
Traffic lights at the intersection of Highway 3 and Cabana Road West will be shut down while new signals are installed. Windsor Police will be on site to direct traffic during the temporary outage.
7 a.m. to 5 p.m., Thursday, December 7, 2023 |
Jane He, P.Eng. Engineer III, Engineering Department City of Windsor, 519-255-6257 ext. 6358 Email: jhe@citywindsor.ca |
Amico |
Complete |
None. |
Complete All |
12/07/2023 00:00:00 |
12/07/2023 00:00:00 |
Huron Church Road (From Tecumseh Road West to Girardot Street) |
3/4/2024 |
3/10/2024 |
Monday, March 04, 2024 to Sunday, March 10, 2024 |
Northbound Huron Church Road will have lane restrictions between Tecumseh Road West and Girardot Street for lane repairs.
Monday, March 4, until Sunday, March 10, 2024 (weather permitting) |
Charles Hartford (CJ) Contracts Coordinator Operations 519-255-6560 ext. 4234 |
Piera Con Enterprises Inc. |
Complete |
road |
Complete All |
03/04/2024 00:00:00 |
03/10/2024 00:00:00 |
Jefferson Street (From Coronation Street to South National Street) |
3/1/2024 |
11/25/2024 |
Friday, March 01, 2024 to Monday, November 25, 2024 |
Update: Jefferson Street Intersection and Road Closure
Jefferson Street will be closed between Coronation Street and South National Street for sewer, pavement and watermain rehabilitation work. Neighbourhood residents will only be able to access this section of Jefferson Street at Coronation Street.
As well, the intersection of Jefferson Street and South National Street will be closed for sewer work for approximately two weeks.
Motorists are urged to avoid the area. Detour signs will be in place.
Intersection Closure: Monday, March 4, to Monday, March 22, 2024
Road Closure: Monday, March 4, to Monday, November 25, 2024
64-23 - Jefferson - Pre Construction Notice Letter - FM.pdf
|
Pierfrancesco Ruggeri C.E.T. Technologist III Public Works-Engineering 519-255-6257 ext. 6506 |
SheaRock Construction Group Inc., Sedeem Najor, 519-990-2759 |
Current |
sewer,watermain,road |
Current All |
03/01/2024 00:00:00 |
11/25/2024 00:00:00 |
Kildare Road, Ottawa Street, Ontario Street (From see description to see description) |
3/20/2023 |
6/2/2023 |
Monday, March 20, 2023 to Friday, June 02, 2023 |
The Windsor Utilities Commission will be reconstructing the watermains on:
Kildare Road from Richmond Street to Ottawa Street (Ward 4)
Ottawa Street from Windermere Road to Argyle Road (Ward 4)
Ontario Street from Chilver Road to Monmouth Road (Ward 4)
Canada Post - Please be advised there should be minimal disruption to mail routes. Road, driveway and sidewalk replacement will be very limited.
|
Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 |
SheaRock Construction |
Complete |
watermain |
Complete All |
03/20/2023 00:00:00 |
06/02/2023 00:00:00 |
Lauzon Parkway (From Forest Glade Drive to Cantelon Drive) |
6/6/2023 |
11/1/2023 |
Tuesday, June 06, 2023 to Wednesday, November 01, 2023 |
Reminder: Improvements to Lauzon Parkway will continue until November. Lauzon is reduced to one lane in each direction between Forest Glade Drive and Cantelon Drive for road reconstruction Speeds are reduced as a result. Expect delays and thank you for your patience.
Ongoing until Wednesday, November 1, 2023-Weather permitting
|
Charles Hartford (CJ) Contracts Coordinator Operations 519-255-6560 ext. 4234 |
Piera-Con |
Complete |
road |
Complete All |
06/06/2023 00:00:00 |
11/01/2023 00:00:00 |
Lauzon Parkway (From Canadian Pacific (CP) Rail bridge to South of Twin Oaks) |
7/17/2023 |
7/20/2023 |
Monday, July 17, 2023 to Thursday, July 20, 2023 |
Lauzon Parkway will be reduced to one lane in each direction over the Canadian Pacific (CP) Rail bridge (south of Twin Oaks) for surface asphalt, milling and paving work.
Monday, July 17, until Wednesday July 19, 2023 (weather permitting) |
Charles Hartford (CJ) Contracts Coordinator Operations 519-255-6560 ext. 4234 |
Front Construction Industries |
Complete |
road |
Complete All |
07/17/2023 00:00:00 |
07/20/2023 00:00:00 |
Lauzon Parkway (From Cantelon Drive to Forest Glade Drive) |
11/27/2023 |
12/11/2023 |
Monday, November 27, 2023 to Monday, December 11, 2023 |
Phase 2 of the Lauzon Parkway Road Reconstruciton Project has been extended, with work on the lanes between Cantelon Drive and Forest Glade Drive. Thank you for your patience, as delays can be expected.
Project continues until Monday, December 11, 2023 (weather permitting - time of day to be determined)
|
Charles Hartford (CJ) Contracts Coordinator Operations 519-255-6560 ext. 4234 |
Piera Con Enterprises Inc. |
Complete |
road |
Complete All |
11/27/2023 00:00:00 |
12/11/2023 00:00:00 |
Lillian Avenue (From Giles Boulevard to Allendale Street) |
10/16/2023 |
12/22/2023 |
Monday, October 16, 2023 to Friday, December 22, 2023 |
As part of an ongoing infrastructure renewal program, the Windsor Utilities Commission (WUC) will be installing a new 200mm PVC watermain on Lillian Avenue from Giles Blvd. to Allendale street and Allendale Street from Lillian Avenue to Howard Avenue. Upon completion of the watermain work the City of Windsor will reconstruct the road.
15-23 Pre-C Letter Lillian Allendale.pdf
|
Enwin Utilities 519-251-7300 ext. 824 |
Sterling Ridge, Greg Czarnecki, 519-978-3111 |
Complete |
watermain |
Complete All |
10/16/2023 00:00:00 |
12/22/2023 00:00:00 |
McDougall Street (From Foch Avenue to 2450 McDougall Avenue) |
7/24/2023 |
7/27/2023 |
Monday, July 24, 2023 to Thursday, July 27, 2023 |
North and southbound McDougall Street will have alternating lane restrictions between Foch Avenue and 2450 McDougall Avenue (City Parks building) for sewer work.
7 a.m. to 7 p.m., Monday, July 24, until Thursday, July 27, 2023
|
Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 |
DanRuss |
Complete |
sewer |
Complete All |
07/24/2023 00:00:00 |
07/27/2023 00:00:00 |
McDougall Street (From Giles Boulevard to Erie Street) |
9/19/2023 |
9/19/2023 |
Tuesday, September 19, 2023 |
McDougall Street will have lane restrictions between Giles Boulevard and Erie Street for retaining wall repairs. Flag persons will be present.
9a.m. to 3p.m., Monday, September 18, 2023 |
Roberta Harrison Coordinator, 519-255-6560 x4241 |
Villa Construction |
Complete |
None. |
Complete All |
09/19/2023 00:00:00 |
09/19/2023 00:00:00 |
McEwan Avenue (From Refer to Description to Refer to Description) |
9/5/2023 |
12/22/2023 |
Tuesday, September 05, 2023 to Friday, December 22, 2023 |
McEwan Avenue between Laing Street and Grove Drive and Laing Street between Campbell Avenue and Curry Avenue will be closed. Road and Sewer rehabilitation project till December 22, 2023.
Local Traffic only.
|
Rajan Ray, Project Manager, 519-255-6257 ext. 6168 |
Sherway Contracting (Windsor) Limited |
Complete |
road,sewer |
Complete All |
09/05/2023 00:00:00 |
12/22/2023 00:00:00 |
McHugh Street (From McHugh Street to Darfield Road) |
1/16/2024 |
1/26/2024 |
Tuesday, January 16, 2024 to Friday, January 26, 2024 |
The traffic signals at Darfield Road and McHugh Street are under repair for approximately 10 days, and as a result, the intersection will be controlled with a two-way stop on Darfield temporarily.
It is recommended that drivers choose an alternate route to cross McHugh Street during this time, as turning on McHugh may be difficult. |
To be determined.
|
To be determined.
|
Complete |
None. |
Complete All |
01/16/2024 00:00:00 |
01/26/2024 00:00:00 |
McHugh Street (From Darfield Road to McHugh Street) |
1/29/2024 |
2/16/2024 |
Monday, January 29, 2024 to Friday, February 16, 2024 |
Plans to install new traffic lights at Darfield Road and McHugh Street this week have been delayed because of bad weather and are now expected to take place within the next two weeks.
Contractors did get concrete for traffic pole base poured, but the installation of the pole will take a little more time. Once the traffic signals are installed and energized, they'll be inspected by the Electrical Safety Authority(ESA).
A two-way stop remains in place, and it is recommended that drivers choose alternate route to cross McHugh Street during this time, as turning on McHugh Street may be difficult. |
Update |
To be determined.
|
Complete |
None. |
Complete All |
01/29/2024 00:00:00 |
02/16/2024 00:00:00 |
Morton Drive (From Ojibway Parkway to Morton Industrial Drive) |
9/19/2023 |
9/19/2023 |
Tuesday, September 19, 2023 |
Morton Drive will be closed at the ETR tracks between Ojibway Parkway and Morton Industrial Drive for Railroad repairs.
Between 7a.m. to 7p.m., September 19, 2023
|
Roberta Harrison Coordinator, 519-255-6560 x4241 |
Essex Terminal Railway |
Complete |
railroad |
Complete All |
09/19/2023 00:00:00 |
09/19/2023 00:00:00 |
Niagara Street (From Marentette Avenue to Parent Avenue) |
3/13/2024 |
3/15/2024 |
Wednesday, March 13, 2024 to Friday, March 15, 2024 |
Niagara Street is closed from Marentette Avenue to Parent Avenue for sewer and watermain rehabilitation. The intersection at Niagara Street and Elsmere Avenue is closed during construction.
Local traffic only.
March 15th to March 19th, 2024 (weather permitting) |
Matt Lemmon, EIT, Engineer I, Public Works-Operations, 519-255-6560 ext. 6305 |
Major Construction (2010) Ltd.,Addy Al-Abbas, 519-256-3971 |
Complete |
watermain,sewer |
Complete All |
03/13/2024 00:00:00 |
03/15/2024 00:00:00 |
Ouellette Avenue (From Tecumseh Road to Eugenie Street) |
5/1/2023 |
10/4/2023 |
Monday, May 01, 2023 to Wednesday, October 04, 2023 |
Ouellette Avenue will be reduced to one lane in each direction from Tecumseh Road to Eugenie Avenue for road and bridge repair work from May 1, 2023 to October 4, 2023.
|
Zoran Savic, Contracts Supervisor Operations (519) 255-6560 x4231 |
Sterling Ridge Infrastructure Inc., 519-978-3111 x2543, jpirillo@sterlingridgegroup.com |
Complete |
road,bridge |
Complete All |
05/01/2023 00:00:00 |
10/04/2023 00:00:00 |
Ouellette Avenue (From Giles Boulevard to Pine Street) |
10/10/2023 |
10/11/2023 |
Tuesday, October 10, 2023 to Wednesday, October 11, 2023 |
Southbound Ouellette Avenue will have lane restrictions between Giles Boulevard and Pine Street for catch basin repairs.
8 a.m. to 5 p.m., October 10 and October 11, 2023 |
Roberta Harrison Coordinator, 519-255-6560 x4241 |
DanRuss |
Complete |
catch basin |
Complete All |
10/10/2023 00:00:00 |
10/11/2023 00:00:00 |
Ouellette Avenue (From Tecumseh Road to Eugenie Avenue) |
12/18/2023 |
12/20/2023 |
Monday, December 18, 2023 to Wednesday, December 20, 2023 |
Ouellette Avenue Overpass located between Tecumseh Road and Eugenie Avenue will be reduced to one lane in each direction for bridge repair work.
Construction crews will be blocking the outside lanes in each direction.
Monday, December 18, 2023 to Wednesday, December 20, 2023 |
Charles Hartford (CJ) Contracts Coordinator Operations 519-255-6560 ext. 4234 |
Sterling Ridge Infrasturctures Inc. |
Complete |
bridge,road |
Complete All |
12/18/2023 00:00:00 |
12/20/2023 00:00:00 |
Parent Avenue (From Erie Street to Niagara Street) |
9/18/2023 |
12/1/2023 |
Monday, September 18, 2023 to Friday, December 01, 2023 |
Parent Avenue between Erie Street East and Niagara Street will be closed for watermain and road rehabilitaion. Local traffic only.
September 18, 2023-October 27, 2023--Weather permitting
|
Charles Hartford Contracts Coordinator Operations 519-255-6560 ext. 4234 |
Sterling Ridge Infrastructure Inc. |
Complete |
watermain,road |
Complete All |
09/18/2023 00:00:00 |
12/01/2023 00:00:00 |
Parkside Court (From Beals Street West to 1548 Parkside Court) |
11/16/2020 |
12/7/2020 |
Monday, November 16, 2020 to Monday, December 07, 2020 |
Parkside Court will be closed from Beals Street West to 1548 Parkside Court for Watermain Reconstruction.
|
Spencer Johnston, WUC 519-251-7300 x 609 |
To be determined.
|
Complete |
watermain |
Complete All |
11/16/2020 00:00:00 |
12/07/2020 00:00:00 |
Plymouth Drive (From Pillette Road to Tourangeau ROad) |
8/8/2023 |
8/22/2023 |
Tuesday, August 08, 2023 to Tuesday, August 22, 2023 |
Plymouth Drive will have lane restrictions from Pillette Road to Tourangeau Road for sidewalk reconstruction. |
Roberta Harrison Coordinator, 519-255-6560 x4241 |
Piera Con |
Complete |
sidewalk |
Complete All |
08/08/2023 00:00:00 |
08/22/2023 00:00:00 |
Provincial Road (From see description to see description) |
3/13/2023 |
11/30/2023 |
Monday, March 13, 2023 to Thursday, November 30, 2023 |
Installation of storm sewer, watermain, concrete road, multi-use trails and streetlights on Provincial Road between South of Cabana Road East to Legacy Park Drive and on Sixth Concession Road from Cabana Road East to CN Rail. Alternating traffic lanes.
Sixth Concession Road from Provincial Road to Cabana Road will be closed for construction on Tuesday, May 23, 2023 until Friday, September 15th, 2023.
Sixth Concession Road from Provincial Road to CN Rail will be closed for construction until Thursday, Noivember 30th, 2023.
|
Paul Mourad, P. Eng. (519) 255-6100 x6119 |
Green Infrastructure Partners Inc. |
Complete |
sewer,road,watermain |
Complete All |
03/13/2023 00:00:00 |
11/30/2023 00:00:00 |
Provincial Road (From Legacy Park Drive to Cabana Road) |
11/17/2023 |
11/17/2023 |
Friday, November 17, 2023 |
Provincial Road will be reduced to one lane between Legacy Park Drive and Cabana Road for road paving. Flag person will be present. Expect delays.
Friday, November 17, 2023
7 a.m. to 7 p.m. |
Paul Mourad, Eng. Engineer III Engineering 519-562-2448 |
Green Infrastructure Partners (GIP) |
Complete |
road |
Complete All |
11/17/2023 00:00:00 |
11/17/2023 00:00:00 |
Riberdy Road (From EC Row to Foster Ave) |
7/4/2022 |
9/23/2022 |
Monday, July 04, 2022 to Friday, September 23, 2022 |
The Windsor Utilities Commission will be reconstructing the watermains on:
Riberdy Road from EC Row to Foster Ave.
WUC Contract 2022-014 Pre-Construction Letter Riberdy.pdf
|
Spencer Johnston, Manager Water Construction & Design (519)251-7300 x609 |
SheaRock Construction |
Complete |
watermain |
Complete All |
07/04/2022 00:00:00 |
09/23/2022 00:00:00 |
Riverside Drive East (From Jefferson Boulevard to St. Rose Avenue) |
9/14/2023 |
11/13/2023 |
Thursday, September 14, 2023 to Monday, November 13, 2023 |
Riverside Drive East- Jefferson Boulevard to St. Rose Avenue.
Enbridge work for gas main installation.
Daytime weekday road closed. Local traffic only.
JSayer@aecon.com ; Will.Ceccacci@enbridge.com ; chrishann@enbridge.com
|
Adam Mourad, P. Eng. (519) 255-6100 x6614 |
Enbridge/AECON Group Inc. 519-726-7361 |
Complete |
None. |
Complete All |
09/14/2023 00:00:00 |
11/13/2023 00:00:00 |
Riverside Drive East (From Patrice Drive to St. Rose Avenue) |
2/2/2024 |
2/2/2024 |
Friday, February 02, 2024 |
Eastbound Riverside Drive East will have lane restrictions between Patrice Drive and St. Rose Avenue for catch basin repairs.
8:30 a.m. to 4:30 p.m., Friday, February 2, 2024 |
Roberta Harrison, Coordinator Maintenance Operations 519-255-6560 ext. 4241 |
DanRuss |
Complete |
catch basin |
Complete All |
02/02/2024 00:00:00 |
02/02/2024 00:00:00 |
Sandwich Street (From Refer to Description to Refer to Description) |
9/5/2023 |
12/12/2023 |
Tuesday, September 05, 2023 to Tuesday, December 12, 2023 |
Sandwich Street Reconstruction PH2.2
Sandwich Street between Essex Terminal Railway (ETR) tracks and Chappell Avenue partial road closure for approximately 14 weeks total.
Northbound traffic: One lane of northbound traffic will remain in place.
- During this closure, businesses located on this section of Sandwich Street will be accessible via northbound Sandwich Street only. Southbound traffic will be detoured to Huron Church Road:
- Vehicular traffic will turn east on Prince Road and follow it to Huron Church Road.
- Commercial (truck) traffic will turn east on Prince Road and then east on Tecumseh Road to Huron Church.
- Once traffic has reached Huron Church Road the detour ends. Huron Church Road can be followed to reach the intended destination of E.C. Row Expressway, Highway 401, Ojibway Parkway or addresses on Sandwich Street within the construction area.
- NEW: Closing the EB lane on Chappell from Russell to Sandwich
Weather permitting September 5, 2023 to December 12, 2023
Questions, email info@wdbridge.com or Sandwich Community Office on Tuesdays and Thursdays between 10:00 a.m. - 4:00 p.m.
|
Windsor Detroit Bridge Authority, (WDBA), Phone 1-844-3221773 |
Bridging North America (BNA) contracted by Windsor-Detroit Bridge Authority (WDBA) |
Complete |
None. |
Complete All |
09/05/2023 00:00:00 |
12/12/2023 00:00:00 |
Sandwich Street (see description) |
11/4/2023 |
11/4/2023 |
Saturday, November 04, 2023 |
On November 4, 2023, Bridging North America will close Sandwich Street in both directions between the Essex Terminal Railway (ETR) easement and Chappell Avenue for paving activities. This closure will be in place from 3 a.m. to 7 p.m.
Following this one-day closure, traffic will return to the current one-lane northbound configuration.
Detour routes are as follows:
Southbound traffic: Southbound traffic will detour to Huron Church Road:
o Vehicular traffic will turn east on Prince Road and follow it to Huron Church Road
o Commercial (truck) traffic will turn east on Prince Road and then east on Tecumseh Road to Huron Church Road.
o Once traffic has reached Huron Church Road the detour ends. Huron Church Road can be followed to reach the intended destination of E.C. Row Expressway, Highway 401, Ojibway Parkway or addresses on Sandwich Street within the construction work area.
Northbound traffic: Northbound traffic will be redirected prior to entering Sandwich Street in the following manner:
o Vehicular traffic coming from Ojibway Parkway (northbound) will continue on E.C. Row Expressway (eastbound) and exit on Huron Church Road northbound, turn northwest onto Prince Road and continue toward Sandwich Street.
o Vehicular traffic coming from E.C. Row Expressway(eastbound) will exit on Huron Church Road northbound, turn northwest onto Prince Road and continue towards Sandwich Street.
o Commercial (truck) traffic coming from Ojibway Parkway (northbound) will continue on E.C. Row Expressway (eastbound) and exit on Huron Church Road northbound, turn west onto Tecumseh Road W, northwest onto Prince Road, and continue toward Sandwich Street.
o Commercial (truck) traffic coming from E.C. Row Expressway (eastbound) will exit on Huron Church Road northbound, turn west onto Tecumseh Road W, northwest onto Prince Road, and continue toward Sandwich Street.
TCP2023328 Sandwich Recon PH2.2 - Full Day Closure TCP Nov 4.pdf |
info@wdbridge.com |
Bridging North America (BNA) hired by Windsor-Detroit Bridge Authority (WDBA) |
Complete |
road |
Complete All |
11/04/2023 00:00:00 |
11/04/2023 00:00:00 |
Sandwich Street Lane Shifting (From Chappell Avenue to ETR) |
1/29/2024 |
2/9/2024 |
Monday, January 29, 2024 to Friday, February 09, 2024 |
Watch for Lane shifting on Sandwich Street between Essex Terminal Railway tracks and Chappell Avenue.
Crews will be completing underground work. Signage and detour barriers will be in place.
Please reduce speed through the area. |
Josie Liburdi, Project Coordinator, Eng., 519-255-6257 x6145 |
Liquiforce |
Complete |
None. |
Complete All |
01/29/2024 00:00:00 |
02/09/2024 00:00:00 |
Seminole Street and St. Luke Road Intersection (Details pending) |
8/14/2023 |
8/18/2023 |
Monday, August 14, 2023 to Friday, August 18, 2023 |
Seminole Street and St. Luke Road Intersection will be closed for road construction. No Emergency Access.
|
Sarah Meneses, Engineering, (519)255-6100 x6336 |
D'Amore Construction (2000) Ltd. |
Complete |
road |
Complete All |
08/14/2023 00:00:00 |
08/18/2023 00:00:00 |
Sixth Concession (From CN Rail to Provincial Road) |
10/7/2023 |
12/1/2023 |
Saturday, October 07, 2023 to Friday, December 01, 2023 |
Sixth Concession will be closed between Provincial Road and the CN Rail tracks for construction.
Emergency traffic Only.
|
Paul Mourad, Project Manager, (519) 255-6100 x6119 |
Green Infrastructure Partners |
Complete |
road |
Complete All |
10/07/2023 00:00:00 |
12/01/2023 00:00:00 |
Sixth Concession Road (From Provincial Road to Cabana Road East) |
8/3/2023 |
9/1/2023 |
Thursday, August 03, 2023 to Friday, September 01, 2023 |
Sixth Concession Rd from Provincial Rd to Cabana Rd will be closed for construction effective Thursday, August 3, 2023 at 2pm until Friday, September 1, 2023 at 6pm.
|
Paul Mourad, Project Manager, (519) 255-6100 x6119 |
Dillon Consulting Limited |
Complete |
road |
Complete All |
08/03/2023 00:00:00 |
09/01/2023 00:00:00 |
Tecumseh Road East (From Forest Glade Drive to Clover Avenue) |
3/10/2021 8:00 AM |
3/11/2021 5:00 PM |
Wednesday, March 10, 2021 8:00 AM to Thursday, March 11, 2021 5:00 PM |
Tecumseh Road East currently has eastbound lane restrictions between Forest Glade and Clover Avenue for catch basin repairs. |
Roberta Harrison, Maintinance Corrdinator, (519) 266-65660 x4241 |
DanRuss |
Complete |
sewer |
Complete All |
03/10/2021 08:00:00 |
03/11/2021 17:00:00 |
Tecumseh Road East (From Howard Avenue to Marentette Avenue) |
3/4/2024 |
3/6/2024 |
Monday, March 04, 2024 to Wednesday, March 06, 2024 |
The westbound curb lane of Tecumseh Road East will have lane restrictions between Howard Avenue and Marentette Avenue for catch basin repairs.
8 a.m. to 3 p.m., Ongoing until Wednesday, March 6, 2024 |
Roberta Harrison, Coordinator Maintenance Operations 519-255-6560 ext. 4241 |
DanRuss |
Complete |
catch basin |
Complete All |
03/04/2024 00:00:00 |
03/06/2024 00:00:00 |
Tecumseh Road East (From see description to see description) |
3/18/2024 |
11/1/2024 |
Monday, March 18, 2024 to Friday, November 01, 2024 |
Windsor Utilities Commission (WUC) will be installing a new 1200mm Concrete watermain.
Turner Road-Memorial Drive to Tecumseh Road East
Tecumseh Road East-Turner Road to Factoria Road
Factoria Road-Tecumseh Road East to Milloy Street
Milloy Street-Factoria Road to Chandler Road
Week of March 18, to approximately November 1, 2024 (weather dependent)
WUC Contract 2024-001CCFM.pdf
|
Enwin Call Centre, Enwin Utilities, 519-255-2727 option 3 |
Sterling Ridge Infrasturctures Inc., Joe DeThomasis, 519-978-3111, ext 2527 |
Current |
watermain,road |
Current All |
03/18/2024 00:00:00 |
11/01/2024 00:00:00 |
Tecumseh Road West (From Mark Avenue to Curry Avenue) |
8/9/2023 |
8/30/2023 |
Wednesday, August 09, 2023 to Wednesday, August 30, 2023 |
Tecumseh Road West Eastbound lane will have restrictions between Mark Avenue and Curry Avenue for road panel replacement.
|
Roberta Harrison Coordinator, 519-255-6560 x4241 |
Giori Construction |
Complete |
road |
Complete All |
08/09/2023 00:00:00 |
08/30/2023 00:00:00 |
Villaire Avenue, St Louis Avenue and Reedmere Road (From see description to see description) |
2/6/2023 |
3/31/2023 |
Monday, February 06, 2023 to Friday, March 31, 2023 |
The Windsor Utilities Commission will be reconstructing the watermains on:
Villaire Avenue from Wyandotte Street East to Riverside Drive East (Ward 6)
St Louis Avenue from Wyandotte Street East to Riverside Drive East (Ward 6)
Reedmere Road from Wyandotte Street East to Riverside Drive East (Ward 6)
The start date has been set for the week of February 6th weather permitting. Please be advised there should be minimal disruption to mail routes. Road and driveway and sidewalk replacement will be very limited.
WUC Contract 2022-056 Pre Letter VSR.pdf
|
Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 |
SheaRock Construction |
Complete |
watermain |
Complete All |
02/06/2023 00:00:00 |
03/31/2023 00:00:00 |
Walker Road, Ontario Street, Montreuil Avenue, Edna Street (From see description to see description) |
5/8/2023 |
8/11/2023 |
Monday, May 08, 2023 to Friday, August 11, 2023 |
As part of an ongoing infrastructure renewal program, the Windsor Utilities Commission (WUC) will be installing a new 200mm PVC watermain on Ontario Street from Monmouth Road to Walker Road and on Edna Street from Montreuil Avenue to St. Luke Road, as well as a new 300 PVC watermain on Walker Road from Richmond Street to Ontario Street and on Montreuil Avenue from Wyandotte Street East to Edna Street as well as a new 400mm PVC watermain on Walker Road from Tuscarora Street to Richmond Street.
|
Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 |
SheaRock Construction |
Complete |
watermain |
Complete All |
05/08/2023 00:00:00 |
08/11/2023 00:00:00 |
Wellesley Avenue (From see description to see description) |
4/10/2023 |
9/1/2023 |
Monday, April 10, 2023 to Friday, September 01, 2023 |
Wellesley Avenue will be closed between Terminal Street and Ypres Avenue for a sewer and pavement rehabilitation. Local traffic only.
Vimy Avenue will be closed between Wellesley Avenue and Forest Avenue. No through traffic, detour signs will be in place.
From Monday, April 10, 2023 to Friday, September 1, 2023 (weather permitting)
The intersection of Wellesley Avenue and Terminal Street will be closed for road work on Thursday, June 1, 2023 from 7:00am to 6:00pm.
|
Pierfrancesco Ruggeri, C.E.T. Technologist III 519-255-6257 x6506 |
GIP Paving Inc. |
Complete |
sewer,road |
Complete All |
04/10/2023 00:00:00 |
09/01/2023 00:00:00 |
Wildwood Drive (From Deerbrook Drive to Halpin Road) |
6/22/2023 |
7/6/2023 |
Thursday, June 22, 2023 to Thursday, July 06, 2023 |
Eastbound Wildwood Drive will have lane restrictions between Deerbrook Drive and Halpin Road for sidewalk repairs. Flag person will be present.
From Thursday, June 22, until Thursday, July 6, 2023
|
Roberta Harrison, Coordinator Maintenance Operations 519-255-6560 ext. 4241 |
Piera-Con |
Complete |
sidewalk |
Complete All |
06/22/2023 00:00:00 |
07/06/2023 00:00:00 |
Windsor Avenue (From Giles Boulevard to Erie Street East) |
11/1/2023 |
12/22/2023 |
Wednesday, November 01, 2023 to Friday, December 22, 2023 |
Windsor Avenue is closed between Giles Boulevard and Erie Street for watermain and road resurfacing. Local traffic only.
Ongoing to Friday, December 22, 2023 - weather permitting
|
Charles Hartford (CJ) Contracts Coordinator Operations 519-255-6560 ext. 4234 |
Nevan Construction |
Complete |
watermain,road |
Complete All |
11/01/2023 00:00:00 |
12/22/2023 00:00:00 |
Windsor Avenue (From Windsor Avenue, Park Street to Goyeau Street) |
3/12/2024 |
4/5/2024 |
Tuesday, March 12, 2024 to Friday, April 05, 2024 |
Manhole and conduit installation work will result in limited on-street metered parking periodically on Windsor Avenue, Park Street and Goyeau Street. Meters will be covered. All driveways and entrances to businesses and parking lots will remain accessible.
8 a.m. to 5 p.m., Tuesday, March 12, until Friday, April 5, 2024 (weather permitting)
Construction Notice Downtown.pdf |
Prem Patel, Acting Manager of Traffic Operations, Operations, 519-255-6247 (ext. 6036) |
BXF Infrastructures Inc. |
Current |
None. |
Current All |
03/12/2024 00:00:00 |
04/05/2024 00:00:00 |
Wyandotte Street East (From Watson Avenue to Isack Avenue) |
4/10/2023 |
5/5/2023 |
Monday, April 10, 2023 to Friday, May 05, 2023 |
Wyandotte Street East from Watson Avenue to Isack Avenue will have lane closures for the construction of a lane widening. There will be periods of time that access to driveways will be limited during construction, the contractor will make every effort to keep inconveniences to a minimum.
Construction is scheduled to begin on the week of April 10, 2023 with an estimated completion date of May 2023.
|
Shannon Mills, Technologist III - Engineering 519-255-6257 x6635 |
SheaRock Construction Group Inc. |
Complete |
road |
Complete All |
04/10/2023 00:00:00 |
05/05/2023 00:00:00 |
Wyandotte Street East (From St. Luke Road to Albert Road) |
8/15/2023 |
8/16/2023 |
Tuesday, August 15, 2023 to Wednesday, August 16, 2023 |
Eastbound Wyandotte Street East will have lane restrictions from St. Luke Road to Albert Road for catch basin repairs.
8a.m. to 5p.m., Tuesday, August 15, and Wednesday, August 16, 2023 |
Roberta Harrison, Coordinator Maintenance Operations 519-255-6560 ext. 4241 |
DanRuss |
Complete |
catch basin |
Complete All |
08/15/2023 00:00:00 |
08/16/2023 00:00:00 |
Wyandotte Street East (From Janisse Drive to St. Rose Avenue) |
12/4/2023 |
12/5/2023 |
Monday, December 04, 2023 to Tuesday, December 05, 2023 |
Eastbound Wyandotte Street East will have lane restrictions between Janisse Drive and St. Rose Avenue for catch basin repairs.
8 a.m. to 3 p.m., Monday, December 4, and Tuesday, December 5, 2023 |
Roberta Harrison, Coordinator Maintenance Operations 519-255-6560 ext. 4241 |
DanRuss |
Complete |
catch basin |
Complete All |
12/04/2023 00:00:00 |
12/05/2023 00:00:00 |
Wyandotte Street East (From Strabane Avenue to St. Rose Avenue) |
3/4/2024 |
3/29/2024 |
Monday, March 04, 2024 to Friday, March 29, 2024 |
Extended:
Wyandotte Street East will have lane restrictions between Strabane Avenue and St. Rose Avenue for conduit installation work.
8 a.m. to 5 p.m., January 29 until March 28, 2024
|
Prem Patel, Traffic Operatoins, 519-255-6267 ext. 6036 |
BXF Infrastructures Inc. |
Current |
None. |
Current All |
03/04/2024 00:00:00 |
03/29/2024 00:00:00 |